Monorail phase II deadline revised for 13th time

During the construction of second phase of Monorail, most time went into erecting piers and launching guideway beam above Wadala and Currey Road railway tracks, as permissions from the railways were awaited.

Latest News
article-main
FacebookTwitterWhatsappLinkedin

The deadline to complete Monorail work between Wadala depot and Jacob Circle has been revised for the 13th time, with the latest deadline being December 2016.

Sources said though a major portion of civil construction was done by Larsen and Toubro, a lot of work still needs to be completed. "A lot of station building work is done, but finishing works are pending, including signalling and electrification," said an official.

It is not just the installation of systems that is pending. Even the five monorail trains are yet to arrive from Malaysia to Mumbai. Once they reach Mumbai and if the guideway beam, on which the monorail runs, is ready with the systems, it will take at least a couple of months for various types of trials and tests.

During the construction of second phase of Monorail, most time went into erecting piers and launching guideway beam above Wadala and Currey Road railway tracks, as permissions from the railways were awaited. It was only in June and September 2015, that the girders were launched over the rail lines.

The first-ever deadline for the project, set by the Mumbai Metropolitan Region Development Authority (MMRDA) officials, was March 2010. Sources said that despite the fact that work was far from over, the MMRDA authorities set ambitious and impractical deadlines.

An MMRDA official said, "We have to set deadlines to push the contractor towards finishing the project. Else, it will keep on dragging, even though we have penalty clauses in the contract."

Phase I deadlines (Chembur-Wadala Depot)

March 2010
December 2010
May 2011
November 2011
May 2012
December 2012
June 2013
August 2013
September 2013
October 2013
December 2013
January 2014
Inauguration: February 1

Phase II deadlines (Wadala Depot-Jacob Circle)

March 2010
December 2010
May 2011
December 2011
May 2012
December 2012
December 2013
June 2014
December 2014
March 2015
December 2015
April 2016
December 2016