Miffed monorail operator says MMRDA risking public safety

Authority had terminated contract of consortium in December 2018

Latest News
article-main
FacebookTwitterWhatsappLinkedin

The consortium of Mumbai Monorail operators, namely L&T and Scomi Engineering (LTSE) has alleged that the Mumbai Metropolitan Region Development Authority (MMRDA) does not have the expertise over monorail technology. The consortium, whose contract was terminated by MMRDA in December 2018 alleged that by terminating their contract and taking over commercial operations of Mumbai Monorail, MMRDA has put safety of public and the overall system at high risk. DNA is possession of a communication between LTSE and MMRDA after the contract was terminated in December.

A senior LTSE official confirmed sending the communication via email, but DLN, Murthy, Chief Operating Officer (COO) of Mumbai Monorail at MMRDA told DNA, "They must have drafted, I don't remember seeing such letter." However, MMRDA did not deny receiving the same.

The MMRDA on December 14, 2018 had terminated contract of LTSE citing non-performance. However, LTSE in a December 28, 2018, communication to MMRDA claimed that MMRDA's decision may derail the commercial operations of second phase between Wadala and Mahalaxmi since the authority does not have technical expertise.

The communication sent by LTSE to MMRDA reads: "Considering MMRDA's lack of expertise in operating and maintaining Monorail technology and its refusal to partake in a smooth takeover, it is inconceivable as to how termination of contract is in larger public interest. We reiterate that by the action of this premature and abrupt termination of the contract, the complete Monorail system and its operations and maintenance has been put at risk."

The MMRDA while terminating the contract had cited a host of issues, including 'persistently disregarding instructions', failure to start the second phase and failure to supply the balance five trains. Currently, 10 trains are in India of which only four are functional. The second phase of monorail got operational on March 4, 2019 while the first phase between Chembur and Wadala was operational in February 2014. The latter was in news for frequent breakdowns and technical glitches.

LTSE has also blamed MMRDA for poor financial condition. LTSE's letter states: "It is also a matter of record that repeated breaches of the contract by the employer (MMRDA), including refusal to nominate arbitral panel for adjudication of disputes on multiple occasions, have constrained contractor to take legal proceedings."

LTSE has claimed that the amount of around Rs 1,800 crore under dispute that has been denied by MMRDA has actually impacted the financial capability of contractor LTSE to infuse funds on its own to make the system functional.