Civil aviation ministry plans to seek detailed explanation on rising bills.
The ministry of civil aviation is planning to once again ask GMR, which leads the consortium developing the Delhi International Airport (DIAL), for a detailed explanation over cost overrun.
The current estimate pegs the cost of modernising this airport at Rs 12,700 crore, significantly higher than the earlier-projected Rs 9,875 crore.
The ministry had written to GMR in April this year, too, but did not get details of projects which led to an overall cost overrun.
A ministry official told DNA, “We had asked DIAL to explain how and when costs escalated but they haven’t explained. We will write to them again… we need details of which specific projects within the airport led to overall cost escalation.”
He gave several examples of how, while constructing the new integrated terminal building, T3, GMR has overshot its own estimates given earlier.
“Glass work was extended to a much larger area without any previous planning to make the airport look good. Even the number of aerobridges was increased, which led to an increase in the terminal area and subsequently the overall cost for building T3. Earlier, GMR had projected that 70% of passenger traffic would use aerobridges but later changed this to over 90%… as many as 15 new aerobridges were added to the original plan.”
Sidharath Kapur, chief financial officer (airports) of GMR, said his company is cooperating fully with the Airport Economic Regulatory Authority (AERA), which has appointed two firms — Engineers India Ltd and KPMG — to conduct cost audit of DIAL.
“Even before we went to AERA, a project cost committee had submitted a comprehensive report on project cost overruns to the DIAL board, where government nominees are also present and this report was then given to AERA,” Kapur said.
AERA’s cost consultants have been conducting their study for the last four weeks.
The ministry official made it clear that the audit by AERA and the ministry’s queries were separate and that similar questions on cost escalation have also been raised with GVK, which is developing the Mumbai International Airport (MIAL).
The official said, as of now, the overall funding shortfall for modernisation of the Delhi Airport stands at Rs 2,600 crore, but of this, Rs 1,800 crore would be bridged through the Airport Development Fee (ADF) being collected since last year.
After GMR’s pleas on funding shortfall, the government had permitted it to charge every departing domestic passenger Rs 200 and every international passenger Rs 1,300.
In May this year, DIAL sought permission to extend the period of this levy by a year, which is when AERA decided to appoint cost auditors.
On its part, AERA has already said that the airport levy should be withdrawn by March next year, instead of the earlier deadline of 2012, citing greater revenue generation through commercial property development at the airport in the interim.
The ministry official said as per current projections, only Rs 500 crore would be generated in 2009-10 but this amount should increase significantly next year because of T3 and the model being used to generate revenues though commercial activities at the new terminal.
The ministry official said that total passenger traffic projected for DIAL in 2009-10 is between 28-29 million when the total airport capacity (after T3 is commissioned) would touch 60 million passengers.
Mukesh Ambani offers MEGA Reliance Jio plans for voice calls, SMS for just Rs...
Sunil Mittal vs Elon Musk: Airtel set to challenge Starlink with this move, will launch...
Deather weather: Temperature falls down to 11 degrees; trains and flights stand delayed
Cristiano Ronaldo creates another record, leaves Lionel Messi behind yet again, creates a unique...
China’s ‘Artificial Sun’ sets new record: Sustains 100-million-degree heat for 18 minutes
Debt-ridden Pakistan makes BIZARRE demand, seeks apology from Elon Musk before...
Grateful for India PM Modi, President Sheikh Zayed for driving relationship, says UAE Ambassador
Oscars 2025: Priyanka Chopra, Guneet Monga's Anuja gets nominated, actress reacts
Donald Trump threatens business leaders with high tariffs: 'If you don't make in America...'
Meet woman, daughter of billionaire whose net worth is Rs 129701 crore, she works as...
Little girl's adorable dance on Diljit Dosanjh's 'Lover' wins hearts online, WATCH clip
Meet man, whose father is missing, mother mentally challenged, yet cleared IIT-JEE with AIR...
DNA TV Show: Four Bollywood celebs, including Kapil Sharma, receive death threats
Virender Sehwag and wife Aarti Ahlawat to call it quits? Report says ‘divorce soon’
10th class student breaks Sourav Ganguly’s long-standing Ranji Trophy record, becomes....
'Good news for everyone': Former Australian tennis star announces divorce, sets up OnlyFans account
This company of Gautam Adani earned Rs 474 crore in just 3 months, its business is...
'Shaam ko mil, tujhe maarta hu': Former India cricketer’s big revelation against Gautam Gambhir
Meet woman, daughter-in-law of pharma billionaire, works in Rs 440000 crore company as...
'Pakistan kya darr gaya?': PCB criticised for ongoing delay in announcing Champions Trophy squad
Mahakumbh Mela 2025: Man dips RCB jersey in Triveni Sangam, prays for team's win in IPL, WATCH clip
ChatGPT Down: Millions of users unable to access AI tool
U19 Women's T20 World Cup: Dominant India beat Sri Lanka by 60 runs, advances to Super 6
Narayana Murthy's Infosys expands its campus in THIS city, to create 17000 new...
'Shah Rukh Khan is a ‘natakwala' first, superstar later'
'No leader other than PM Modi can bend it like Beckham'
Gautam Adani's company's net profit jumps 73% in just 92 days, firm earns Rs...
After Gautam Adani, this millionaire visits Mahakumbh Mela with just a small bag, she is...
Jalsa to Vatsa: Here's a look at Amitabh Bachchan’s iconic homes and smart investments
Bhavish Agarwal's Ola, Uber get CCPA notice for alleged differential pricing for...
Monali Thakur denies any breathing issues, wasn't hospitalised
Samsung Galaxy S25 series launched: Price, pre-order deals, full specifications and more
Bhumika Group Earns Prestigious 'Great Place to Work' Certification for 2025-2026
Sky Force: A Skyward Journey of Courage, Sacrifice, and Patriotism
Here’s why Junaid Khan is carrying backpack around during Loveyapa promotions
Can China return to former GDP growth rates?
Guillain-Barré Syndrome: Pune sees 35 suspected cases of rare nerve disorder
Swara Bhaskar reveals being blacklisted in Bollywood: 'There would be a price to pay'
Jalgaon Pushpak Express accident: Death toll rises to 13, Rs 1.5 lakh aid announced for victims
'Sawaar loon' singer Monali Thakur struggles to breathe during live performance, rushed to hospital