Gujarat Industries Power Company Ltd (GIPCL) on Saturday announced delays in commissioning of its 51 MW wind-based power project in Gujarat.

COMMERCIAL BREAK
SCROLL TO CONTINUE READING

"On account of financial difficulties faced by Leitwind Shriram Manufacturing Ltd, Chennai, the EPC contractor, the date of commissioning of the 51 MW wind-based power project in Gujarat has been delayed," GIPCL said in a BSE filing.

The company further said it has been intimating to the exchanges, about the progress of the said project from time to time and "as intimated by the company vide its letter dated March 19, 2016, 8 Wind Energy Generators (WEGs), out of total 34 WEGs, have been commissioned so far."